Budget of the APR

  • There is so little transparency in the evolution of the budget for the works of the TAV, that everyone jokingly receives no news that is generated every time. And nothing to say with the start date. It is shameful to see the Basque Government councillor, Arantxa Tapia, who has competence in this matter, and after saying that, the word is eaten. But Basque Y is not a matter of laughing.

It is a very serious matter from the outset. Seen as “a State issue”, the institutions have never wanted to question, let alone claim a debate and a referendum.

The leaders of this anti-social initiative against citizenship, the governments of Madrid and Vitoria-Gasteiz, budgeted in 2006 a total of 175 kilometers for a work: EUR 4.178 million. Hence 40% through the quota to be paid by the autonomous government of the CAV, EUR 118 million came from European funds and EUR 2500 million would be provided by the Spanish Government. After several dates of completion of the works, it is currently estimated that it will not be launched until 2023, and the cost has increased by EUR 2 billion, to EUR 6 billion. It has been known these days that underground access to the TAV in Vitoria-Gasteiz will cost us EUR 150 million more, 20% more than originally planned, a total of EUR 872.2 million. At the moment, the cost overruns at the Donostia and Bilbao stations are unknown.

Madrid and Vitoria-Gasteiz have never stopped making a democratic debate on an infrastructure such as the TAV, but society needs to know, euros to euros, how and why they are spending the taxes of the citizens on the Pharaonic work. A comparative data: The new hospital in Eibar has cost EUR 28 million, according to the same sources.


You are interested in the channel: Abiadura Handiko Trena
There is a link between Euskal Ya and AHT in Navarre

Do not look for this connection from Ezkio or Altsasu, let alone crossing the Ebro River through Castejón. The connection, or rather the connections, between the Basque Y and the AVE of Navarre is already a reality. It is these links in the plural that should concern us and... [+]


AHTren atzerapena gaitzesteko gutuna bidali diote Europako Batzordeko Garraio Komisarioari Pradalesek eta Roussetek

EAE, Akitania Berria eta Nafarroak osatutako euroeskualdearen batzarra egin dute Iruñean martxoaren 25ean. AHT izan dute topaketaren ondoko agerraldiko aipagai nagusien artean eta Akitania Berriko ardatza Hego Euskal Herriko trenbidearekin lotzeko konpromiso politikoa... [+]


AHTaren zundaketen aurkako ia bi urteko borrokaren balantzea

Datorren udaberrian, Stop AHT Zundaketak ekimenak bi urte beteko ditu. 2023ko maiatzean, ADIFek Itza, Sakana eta Goierriko udalei jakinarazi zien zundaketa geoteknikoak eta beste jarduketa batzuk egingo zituela AHTaren Nafarroako korridorea Euskal Y-arekin lotzeko alternatibak... [+]


Espainiako Sustapen Ministerioa: “Ez dakigu Ezkioko lotunea oso bideragarria den”

Josu Estarrona EH Bilduko Arabako senatariak egindako galderari erantzun dio Espainiako Sustapen Ministerioak, eta hor berretsi du Ezkioko aukera zailtasunez beteta dagoela.


PSNk AHTaren Gasteizko lotunearen alde egin du, Ezkiokoa ez dela “bideragarria” argudiatuta

"Gasteiztik egin ezean, ez da egingo", adierazi du PSNren bozeramaile Ramón Alzorrizek. Kontra azaldu dira Geroa Bai, UPN eta PP.


2025-02-20 | Gedar
Work to start the construction of the AVE between Vitoria and Burgos, moving forward
The first works to connect AVE with AHT Madrid and the AVE train will cost 2 billion euros. A demonstration was held this weekend in Pamplona to denounce the conditions of slavery in the construction works of the AVE.

AAV in the Southern Basque Country: An investment of 15 billion euros to reach Irun at high speed?
A demonstration against the high-speed train will take place in Pamplona this Saturday, called by the platform AHT Pause, at 12:00 hours from the Provincial Council. The construction of the railway line between Castejón and Pamplona continues and the Spanish Ministry of... [+]

Adif says that the situations of labor slavery denounced in the works of the AHT are "false"
After receiving the scandalous testimony that AHT Geldi denounces the existence of situations of labor slavery in the works of the High-Speed Train of Navarre, the company Adif that promotes these works has had to respond publicly: "They're a lie."

AHT Pause denounces the existence of situations of slavery in the works of the AVE of Navarre
The workers of the fast train that is being built in Navarre denounce that they are in a state of slavery during the press conference of the association AHT Pause in Pamplona.

They denounce that the AVE will lead to a large expropriation of agricultural lands in Álava
Representatives of the Añana and Trebiñu gangs, as well as farmers and ranchers in Álava, have denounced that they suffer "enormous institutional contempt" for the work of the AVE. More than two million square meters of “fertile land” will be expropriated in these places... [+]

For a quality public rail service for the Ribera

In recent weeks we have been reading "proposals" for the recovery of the railway line Castec-Soria and the maintenance of the Tudela train station in its current location, or for the construction of a new high-speed station outside the urban area with the excuse of the supposed... [+]


2024-12-18 | ARGIA
The Basque Y will not connect with Ipar Euskal Herria until at least 2042
The French Government has confirmed to the Spanish Government that the High-Speed Train will not reach Hego Euskal Herria (Irun link) until at least 2042 years later. It is not among the priorities of Paris.

TAV: The Spanish Government is considering a "third" alternative for connecting the Basque 'Y'
The Secretary of State for Sustainable Transport in Spain, José Antonio SANTANO, has stated that the Basque Government has admitted a resource on the connection of Ezpied-Itsaso, which would not "harm" Aralar.

2024-11-27 | Julene Flamarique
TAV works in the CAV are delayed until at least 2027
The Basque Government expected the High-Speed Train to be ready by 2027 when the Astigarraga-Hernani stretch ends in February 2024. The Basque Government has now launched a tender for the works of the Arkaute link, which has made available to the company Euskal Trenbide Sarea,... [+]