The solar power plants you want to build in Álava are 25, not three

  • According to data from the Basque Government, the requests for the installation of solar plants in Álava by Solaria Eguzki Generation, SLU, are 25 and affect twelve Alavese municipalities. Of these, 24 are 49.89 MW or more of power: among them, they would total more than 1,234 MW and cover more than 3,455 hectares of land in the districts of Vitoria, Gorbeialdea and Añana. Solaria plans to bring this electric current to Bizkaia, for which it has built a high-voltage line of over 100 kilometres. Sixteen associations have called for a demonstration on 26 October in Vitoria-Gasteiz under the motto 'Underway'.
Erriberabeitian 2020tik dagoen eguzki-zentral honek 55 hektarea hartzen ditu eta EAEko handiena da. Ia hiru bider handiagoa izango da Solariak eraiki nahi dituen 25 zentraletako bakoitza. Argazkia: krean.com

29 August 2024 - 10:25
Last updated: 2024-09-02 12:26

So far, three projects of solar plants that Solaria has presented in Álava have been mentioned in the media: Zierbena Solar 2, 3 and 4. Those intended to be built in Vitoria-Gasteiz, Zigoitia and Ribera Baja in Armiñón and which provides for the construction of a high-voltage line over 100 kilometres that will connect with the substation of Zierbena (Bizkaia). Each of them would be 49.89 MW of power.

They are somewhat larger, each of 49,895 MW, another 21 projects presented by Solaria in the Basque Government, all with the name “Zierbena Solar” ahead of the corresponding number. And there is a slightly smaller project of 36.99 MW.El July 30, the Minister of Industry, Energy Transition and Sustainability, Mikel Jauregi LETAMENDIA, announced this data in response to the request for information from the PP parliamentarian Ana Morales Peral. According to this information from the Basque Government, the 25 projects are in the same situation, “in processing”.

In total over 3,455 hectares

What scope would each of the 25 projects that Solaria wants to carry out in Álava? We have taken as an example the Zierbena Solar 2 project that you want to build in Ribera Baja Armiñón, which you can see on April 22 in the Official Gazette of the Basque Country (BOPV):The forecast is 143.97 hectares (49.89 MW of power). Of the 25 projects, 24 will have the same or slightly higher power and are expected to cover more than 3,455 hectares.

Lands of twelve villages

Three districts of Álava will be affected by these 25 projects of Solaria: Añana, Gorbeialdea and Vitoria. It is the lands of twelve cities and towns that Solaria wants to cover with solar power stations, specifically those listed below.

Vitoria-Gasteiz: it aims to land seven projects (Zierbena Solar 1, 4, 5, 22, 23, 24 and 29, the latter slightly smaller, 36.99 MW).

Zigoitia in the Gorbeialdea region (three projects: Zierbena Solar 1, 3 and 25) and Arratzua-Ubarrundia (two projects: Zierbena Solar 1 and 22).

Valdegovía in the region of Añana (four projects: Zierbena Solar 8, 9, 10, 12), Ribera Alta (four projects: Zierbena Solar 6, 7, 11 and 18), Armiñon (four projects: Zierbena Solar 2, 11, 15 and 17), Lantarón (three projects: Zierbena Solar 9, 10 and 13), Berantevilla (three projects: Zierbena Solar 15, 19 and 21), Zambrana (three projects: Zierbena Solar 16, 19 and 21), Iruña de Oca (two projects: Zierbena Solar 5 and 18), Ribera Baja and Kuartango.

Initiatives against these solar power plants

The Deputy General of Álava, Ramiro González, questioned to the media the suitability of the three projects of Solaria that were then discussed: he claimed that it makes no sense for the production of energy in Álava and the consumption in Bizkaia to cause unnecessary damage to biodiversity.

In July several municipalities submitted claims: Amurrio, Zuia, Ayala, Abanto, Galdames, Gordexola and Zierbena. The Town Hall of Ribera Baja approved a motion against the implementation of large renewable infrastructures in high-strategic value soils.

On 10 July 16 associations submitted more than 50,000 claims to the Zierbena Solar 2, 3 and 4 projects. The associations include Araba Bizirik, Arabako Mendia Aske, AHTrik Ez, and UAGA. And they have called a demonstration for October 26 in Vitoria-Gasteiz to “stop insanity”.

The Lurra network has recently submitted allegations against the high-voltage line from Álava to Bizkaia. Iñaut Matauco explained on 28 July in Berria that allegations have been made of the Zierbena Solar 1 project and denounced that Solaria has committed a "law fraud" by considering that only 8.5% of the electric transport line and processing the Earth as an evacuation line what the network considers a transport line.


You are interested in the channel: Energia berriztagarriak
The government changes its renewable land plan to make more space for large-scale wind turbines
On December 20, the Basque Government approved the provisional version of the plan and a large number of “low and medium” capacity areas are now listed as “medium and high” capacity.

2025-02-04 | Mikel Aramendi
THE ANALYSIS
Will the world’s largest dam that China wants to build burn down?
The announcement by the Chinese government in the last breath of last year that it will launch a large hydroelectric project in the lower basin of the Yarlung Zangbo River, which has not flooded the waters, seems to have set them on fire among us. We can say that the comments... [+]

2025-02-04 | Estitxu Eizagirre
"The energy transition in debate"
Round table between Mikel Otero and Aitziber Sarobe on Wednesday in San Sebastian
On 5 February, Mikel Otero, head of ecological transition at EH Bila, and Aitziber Sarobe, natural conservationist, will take part in a panel discussion in San Sebastian entitled "Energy transition in debate: opportunities and risks". This event is organized jointly by four... [+]

2025-02-03 | Estitxu Eizagirre
The company informs the City Council of Zizurkil that they will not install wind turbines in Ezkeltzu
Green Capital has notified Zizurkil City Council verbally of its decision to "definitively cancel" the Ezkeltzu project. The City Council welcomed the cancellation of the project, which "raised serious doubts about the damage it could cause to the environment, landscape and... [+]

2025-01-27 | Julene Flamarique
Renewable energy beats fossils in EU electricity generation in 2024
Electricity production from gas has declined for the fifth year, and overall fossil electricity generation is at an all-time low, according to Ember’s European Electricity Review.

2024-12-23 | Estitxu Eizagirre
EH Bizirik has mobilized against the plan approved by the Basque Government:
"Overcoming the current capitalist model is fundamental to finding a way out to the ecological and energy emergency"
On 20 December the Basque Government approved the "provisional version" of the Sectoral Territorial Plan for Renewable Energy (PTS), following the tradition that projects that generate social conflict will be approved on the eve of the holiday. EH Activa has concentrated before... [+]

2024-12-17 | Usurbilgo Noaua
There is no wind farm at the moment, on Mt. Ezkeltzu between Usurbil and Zizurkil
The wind farm project, which was planned to be built in Ezkeltzu, will not be implemented for the time being. In February 2022, the intention to build a wind farm in Ezkeltzu was known. From that point on, the subject has taken a journey, but at the moment it seems that the... [+]

2024-12-10 | Leire Ibar
Construction of a new 74,000 panel photovoltaic power plant in Navarra begins
GES-Global Energy Services has launched the solar power generation project in Olite, one of the largest in the Basque Country. It will have a power of 50 MWp and will have a total of 74,000 solar panels, so the facilities are expected to be launched before the end of the... [+]

2024-12-05 | Estitxu Eizagirre
Nine other wind turbines are planned, this time in Beizama and Bidania-Goiatz, in Gipuzkoa
Finerge intends to install nine macro-wind turbines in Beizama and Bidania-Goiatz, of 229.5 meters each, with a combined power of between 45 and 50 MW. Among the windmills, six roads would be built, which would also be taken to the land of Errezil. The company has presented to... [+]

The year of the popular platform Meaka-Irimo
Sometimes we need a threat to know the importance of what is at risk. And the magnitude of that threat depends on the strength that we feel within us to respond to a possible aggression. As soon as you realize, you see yourself working hard to protect those who are at risk of... [+]

2024-11-08 | Egurra Ta Kandela
Strategic lines of the Basque Government
If the reading of the Renewable Energy Sector Territorial Plan (PTS EBB) for farmers and livestock farmers was disappointing – and it was – it was not that it was much happier to read the report of responses to 4,217 allegants in this regard in July 2023. It was published on... [+]

2024-11-05 | Estitxu Eizagirre
Wave of photovoltaic and wind power plants
Álava, daughter who want to sacrifice?
In this report we have put numbers to the rain of renewable energy macroprojects in Hego Euskal Herria. On the map drawn by the data, Navarre remains red alive and Álava concentrates 75.4% of the central energies that companies want to make in the CAV. The projects do, however,... [+]

Urumea Mountains Bizirik
"Wind companies are more proud of small towns"
They are Erramun Galparsoro and Joxe Manuel Muñoz, neighbours of Aranoa, who have died. They have been living in a small town in Navarre, which is about 440 meters high and looks at the sea and has 114 inhabitants, for 22 and 30 years, respectively. The two are part of the... [+]

Eguneraketa berriak daude