Automatically translated from Basque, translation may contain errors. More information here. Elhuyarren itzultzaile automatikoaren logoa

Remírez states that the Government of Spain acts rigorously in the Yesa dam, 22 years after the beginning of the works

  • The Vice-President of the Government of Navarre, Javier Remirez, explained in the Parliament of Navarre a study on the safety of urgency which was completed fifteen months ago and which has not been published so far. The investigation was carried out on behalf of the Government of Spain.
Argazkia: Mikel Urabaien

21 October 2022 - 10:17
Last updated: 15:45

Opposition parties accused him of lack of authority over the Ministry of Ecological Transition and reconsidered the uncertainty of the scientific consequences and the quadrupling of the planned budgets.

If the reservoir were to be filled, safety could not be guaranteed. This is the most striking conclusion of the latest research on the Yesa Reservoir, according to Adolfo Araiz, spokesman for EH Bildu in the Parliament of Navarra, as expressed by his party in the committee convened on 18 October. The report of over 600 pages says that “it is not possible to prove that there is an acceptable safety factor”. In other words, it is not possible to know whether the new dam being built by the Spanish Government would maintain the force of water.

Meanwhile, the work continues. The work of doubling the capacity of the reservoir is extending for 22 years, with no end to be discerned. Concerning the budget, it has been multiplied by 4.5: From EUR 100 to EUR 450 million. “Is it worth it?” asked Marisa de Simon, spokesman for Ezkerr-Ezkerra, Javier Remírez, vice-president of the Government of Navarra.

But this says that the answer “corresponds to the Government of Spain”, which is the manager of the works and the entity that has commissioned the final report. The problem in this case, according to José Suárez, of Navarra Suma, is the lack of authority of Remírez before the Government of Spain, since the Ministry of Ecological Transition received the investigation 15 months ago and did not teach it to the Foral Government until July, at its request.

In the words of Blanca Rodríguez, a colleague of the Remírez party, they expected “stronger security effects.” However, after the summer drought, the reservoir is at historical lows and at present the safety of the downstream inhabitants is not the main concern. According to Podemos spokesman Ainhoa Aznarez, “in 2050 experts consider that the flow of the Aragon River that supplies Esa will be reduced by 26%”. “In view of the climate crisis, being a great prey will serve no purpose.”

In any case, the situation is always harsh: if there were to be a possibility in winter of abruptly filling the reservoir due to torrential rains, all international protocols would force the peoples of Sangüesa and downstream waters to evacuate. In any case, since the filling of the reservoir is going to be very complicated, it does not seem to be going to happen, so the citizens can rest assured. However, we would pay a pricey price for the tranquility of its inhabitants: Over EUR 450 million lost.


You are interested in the channel: Esa urtegia
Closure of the extension of the Esa reservoir
According to the Rio Aragon Association, the expansion of the Esa reservoir is paralyzed by "insecurity". This group requests the suspension of the contract and the revision of the project. They call on the Ebro Hydrographic Confederation to accept "unfeasibility".

2023-09-29
They want to end the expansion of the Esa reservoir by 2027
The works began 22 years ago, but the construction of the reservoir has had many problems, and the works are still going on. In response to the request of Río Aragón, the Confederación Hidrográfica del Ebro, CHE, replies that the work is scheduled for completion in 2027.

Satellite warn of the instability of the Yesa reservoir
Geological studies have warned on more than one occasion and now the warning comes from satellite surveillance: The Yesa reservoir is not stable. Copernicus, the European Union’s Earth observation programme, has detected a ‘movement’ on the slopes of the reservoir.

D. Alfredo Ollero Ojeda
“Rivers are sinking deeper and deeper into their channels”
The Ebro is the largest river in the Basque Country. We have spoken on its shore, at the entrance to Zaragoza, where Ollero lives, accompanied by the slow lertxuna, the crazy song of birds and the gentle flow of the river, the afternoon that has erupted spring at 33 degrees,... [+]

Ingeotyc geology recommends not to extend the Yesa reservoir
It concludes that the right side of the reservoir remains unstable and therefore there is a level of risk. The report was prepared by geologists Valentín Ibarra and Tomás Morales of the company Ingeotyc on behalf of the City Council of Sangüesa.

Extension of the Esa reservoir is welcomed by the report of the Ministry of Transition
Finally, the report of the Government of Spain on the safety of the Yesa reservoir has appeared, which has been “lost”, and allows the work of the reservoir to continue.

They denounce the loss of the report commissioned by the Government of Spain on the Yesa dam
The Spanish Government's Ministry of Transition commissioned the Spanish College of Road and Port Engineers to see what the organization said about the reservoir's viability.

Suspension of the water project from Salazar to Yesa
The Ebro Hydrographic Confederation has withdrawn from its hydrological plan the project of building a dam in the village of Aizpurgi, in the Navarre Pyrenees, and its drive to the Yesa reservoir through an underground canal.

Analysis
Navarre reservoirs below the minimum: What has evidenced the drought?
The dry summer we have had in many places in Euskal Herria is already noticeable. According to data collected by the Ebro Hydrographic Confederation (CHE), the water stored in Navarre is well below the average of the last decade and in the case of the Yesa reservoir is 29% of... [+]

Korrontearen atzetik
Piszinan aurrera eta atzera aspertu egiten dira nonbait, eta 1989ko abenduaz geroztik ibaietan, urtegietan, lakuetan eta itsasoan egin dute igeri. Miño, Ebro, Sil, Bosnia-Herzegovinako Neretva ibaia gerra garaian... Nafarroako Esa urtegia, Eskoziako Ness laku famatua,... [+]

What are the risks of the large Yesa potash mine?
The Muga project, approved by the Government of Spain, provides for a mine of 1,700 hectares between the Navarros municipalities of Xabier and Undués de Lerda, very close to the Yesa reservoir. Experts say it would contaminate the rivers and aquifers in the area, sink the soil... [+]

2020-10-23 | ARGIA
“Remirez lehendakariordeak nafarren segurtasuna arriskuan jartzen du”

Esako urtegiaren inguruan eta azken asteetan Nafarroan izaten ari diren mugimendu sismikoez erakutsitako jarrera dela eta, Sustrai Erakuntzak gogor kritikatu du Javier Remirez Nafarroako Gobernuko presidenteordea eta Babes Zibileko arduraduna. Ondorengo lerroetan irakur daiteke... [+]


Esako urtegiaren lanak ez dira geldituko oraingoz

Azken bi egunetan nahasmen handia egon da Esako urtegia handitzeko lanen inguruan. Asteartean Teresa Ribera Espainiako Gobernuko Trantsizio Ekologikorako ministroak esan zuen ez zela urrats bat gehiago aurrera egingo segurtasuna erabat ziurtatu arte. Aturando Esa (Esa Gelditzen)... [+]


2020-10-07 | ARGIA
Esako urtegiko eskuin hegala ez da oraindik egonkorra, txosten ofizialak aztertuta ondorioztatu dutenez

Uraren Kultura Berria Fundazioak (FNCA gaztelaniazko sigletan) Esako urtegiari buruzko azken txosten ofizialak aztertu ditu eta ondorioztatu du urtegiaren eskuineko hegalak "ezegonkorra" izaten jarraitzen duela eta, beraz, "segurtasuna ez dagoela bermatuta".


2020-08-27 | ARGIA
Esa urtegiak sorturiko arriskua ezkutatu nahi izatea egotzi diete agintari politikoei

"Esan eta manipulazio informatiboa" izeneko idatzia zabaldu dute Esa Ez-Lanak Gelditu eta Río Aragón elkarteek hainbat hedabidetan. Agintari politikoek, azpiegitura horrek dakarren arriskua ezkutatzeko darabilten hizkera salatu dute.


Eguneraketa berriak daude