Sánchez’s government does not reach 5% of the investment needed by the TAV in Navarra

  • The Minister of Transport of the Government of Spain, Raquel Sánchez, who was in Pamplona on Friday, praised the investments made by her government: EUR 103 million in works and EUR 125 million in tenders.
Alesbes Tafalla zatiko argazkia. (Arg.: Ekin Klik)

25 April 2022 - 11:31
Zarata mediatikoz beteriko garai nahasiotan, merkatu logiketatik urrun eta irakurleengandik gertu dagoen kazetaritza beharrezkoa dela uste baduzu, ARGIA bultzatzera animatu nahi zaitugu. Geroz eta gehiago gara, jarrai dezagun txikitik eragiten.

Half of the investment made since 2011 has been executed by the PSOE government, but the TAV section in Navarra is practically zero and A is insufficient. According to the calculation made by Irisarri in Diario de Noticias, the expenditure of the Government of Madrid does not amount to 5% of the total budget. The Navarre section, which connects the city of Zaragoza with the CAV, consists of 232 kilometers and has a budget of 2,469 million euros. The investment thus far affects about 25 kilometres of the Ebro Bank.

The most advanced section of Castezhejiang-Pamplona

This section is 70 kilometres long and has a budget of €1,064 million, according to the calculation made in 2018. The construction is being carried out in this section, it consists of five sections and the only one that is completed is the Caste• Villafranca section, 14.77 kilometres.

The first section is part of the bridge over the Ebro River, which will connect the current section of the TAV to the Tutera-Bilbao railway. It costs EUR 50 million and, as announced by the Government of Navarra, it will raise 40 million of the funds from the European Next Generation. It has not detailed where the other EUR 10 million that Garoña has will come from. It should be recalled that this investment is made entirely by the Government of Spain. It is assumed that the tranches financed by the Government of Navarra would be deducted from the quota.

The second part is the only one that is carried out, the one already mentioned Caste• Villafranca. The third tranche is Villafranca-Villanueva de Aezkoa (EUR 125 million), divided into two other subsections: on the one hand, Villafranca de Peralta, 5 km and very complex, is the most expensive tranche of the TAV of Navarra, as it must pass over the Aragon River and the AP-15 through two high-risk,

The fourth tranche joins Villanueva de Tafalla with 14.67 kilometers and has a budget of 117 million euros, and is operational since 2019. The fifth tranche is the Tatreatments -Campanas, with 15 kilometres and a cost of EUR 128.82 million. The foral government has announced that it will allocate EUR 105.5 million of European funds to this tranche, which will be financed from funds. Nor is there anything built in them.

And from Campanas to Pamplona is the sixth and most complex – the loop of Pamplona –, among other things because the current train station of Pamplona is moved to the district of Etxabakoiz. There is nothing done. This section was of great impact during the UPN administration, as the party on the right intended to build 9,000 houses in the neighborhood to finance the works of the TAV. Last September, the Government of Madrid ruled that it was going to happen in this way.

The sections of Zaragoza and Vitoria-Gasteiz still in the air

In addition to this section in Castezhejiang-Pamplona, the Navarre section of the TAV has two other large sections: the one that joins the foral community from south to Zaragoza (with a budget of 87 and 825 million euros) and from the north to the link Asturias-Vitoria. In the latter there is nothing advanced either, and furthermore the Government of Navarra and the Basque Government do not like it. This part is also key to the rapid connection between the Atlantic and the Mediterranean.

For the Government of Spain, the Basque Government and the Government of Navarra these TAV itineraries are strategic projects, but in two decades it has not yet been possible to complete the Basque Y, and the part of Navarre is in the air, at least in budgetary terms.


You are interested in the channel: Abiadura Handiko Trena
Polls begin in the Otsobi Council land without asking for permission
Preliminary surveys for the construction of the High-Speed Train on Otsobi Council sites have been initiated without information being provided and without request for authorisation. The Stop Surveys platform reports on the situation: "The surveys have been launched without... [+]

They call to mobilize against the TAV project running through Lapurdi
The CADE group, made up of environmental associations, has denounced that the TAV going through Lapurdi is progressing in its development. He has scheduled for 12 and 13 October in Gironde, in support of the protest organised by the Altxuak network on Earth.

Neither galgo nor hunting dog

We have been with the "summer snake" over the TAV for a few weeks and with the possibility of linking the "Basque Y" from Pamplona, from Ezkio or Vitoria.

It is disappointing to see that our People continue to depend on decisions concerned and not supported by the galgos and... [+]


The Spanish Government says that the connection of the TAV with Ezdox-Itsaso has "problems" and bets on that of Vitoria-Gasteiz
The Spanish Minister of Transport, Óscar Puente, has assured that the connection with Navarre "is the most acceptable" in Vitoria-Gasteiz, because the Eztango-Itsaso route has "technical complexity".

Works of the TAV and Renfe: cuts and headaches in the rail service of Gipuzkoa for seven years
Since the beginning of the tunnel excavation in Gaintxurizketa in 2017, the restrictions and conditions of the works of the TAV to the Renfe railway service have been constant. Now, the Spanish Ministry of Transport has announced that this service will be interrupted for several... [+]

2024-06-06 | Jule Goñi
Stop polls, key

In the spring of last year, in Sakana, in Izan and Goierri, flooding was introduced in the municipalities of these areas for the conduct of geological surveys for the works of the TAV. In the canyoning 15 surveys have been requested in the municipalities, from Erro to Olazti /... [+]


Saturday: Day against the TAV in Pamplona

Although immersed in an unprecedented eco-social crisis, the administration continues at all costs with the work of the TAV, destroying the territory and squandering the resources essential to social needs. The works of the Castejón Bridge and the Tafalla Campanas subsection,... [+]


For fair eco-social alternatives, without VAT

Next Saturday, May 11, AHT Gelditu! Navarra organizes in Pamplona the Day against the TAV. In addition, Eco-Socialist Spaces, the World March of Women and the Charter of Social Rights have called a demonstration under the motto For a Dignified Life, A Just Eco-Social... [+]


2024-04-22 | Ahotsa.info
Sakana bets on the public and social train
A massive demonstration in Alsasua calling for the cessation of TAV works and the improvement of the current rail system.

Saturday in Altsasu the demonstration "To make the train a real means of transport"
Actors against the TAV and for the railways will hold a demonstration in Altsasu on Saturday 20 April to call for the renewal of railway infrastructure and the increase in train frequency. The respondents recall the existence of an alternative and ask that this study be... [+]

They discover remains of another Basque town in Navarra and denounce that the works of the TAV can destroy them
In the village of Muru Artederreta, on the hill of Murugain, the wall of an Iron Age village has been discovered while taking samples for TAV works. The community of neighbours denounces that the construction of the mouth of a rail tunnel would destroy part of the wall.

Julio Villanueva (AHT Gelditu)
“Abiadura Handiko Trenik gabeko Nafarroa posible da”

Abiadura Handiko Trenaren inguruan mintzatu dira zenbait ekintzaile asteazkenean Iruñeko Zabaldin osatu duten hitzaldian. Italiako Val Susa bailarako adibidea bertatik bertara ezagutzeko aukera ere izan dute han sortutako mugimenduaren ordezkari bat etorri delako... [+]


Iñaki Arriola notes that to see the works of the TAV completed it will still take a few years
The Councillor for Transport of the Basque Government has acknowledged that citizenship is "tired and annoying" with the duration of the works. It is promised that the works of the concrete infrastructure of the so-called "Basque Y" will end in 2025, but the entire upper structure... [+]