The Government of Navarre advocates amending the law to bring forward the controversial Sangüesa mine

  • The Government of Navarre was surprised at the kick that the mining project Muga de Sangüesa has given from the judicial area. This has been acknowledged by the Ecological Transition Counsellor, Mikel Irujo, at the end of his speech. He said that the Spanish Mining Act should be amended and did not clarify whether the judgment of the Superior Court of Justice of Navarra is to be appealed.
Muga meatzearen ahoa izango litzatekeenaren lehen fasearen irudi bat. Geoalcali

25 October 2024 - 06:43
Last updated: 10:04

The Muga project is the largest mining project in Euskal Herria and the Spanish State to exploit the potash that is to be carried out in Sangüesa and other localities of Aragon. The suspension of the operating permit of the Foral Community by the Superior Court of Justice of Navarre is therefore not barbaric.

Irujo has not clarified whether the judgment will be appealed, although he said that "it is being analysed in detail".

On Wednesday, the Green Transition Counsellor of the Government of Navarra, Mikel Irujo, made a first assessment at the press conference after the Governing Council and defended the management of the project. However, he has admitted that three permits have been granted for a project and that the Spanish Mining Act can prevent something from being done according to interpretations, as the court has said.

But then he attacked that 1973 "pre-constitutional" law, and he said "it needs to be changed." It has also defended the competence of the Foral Community of Navarra in the field of mines. Irujo, for his part, has not wanted to reveal whether the sentence will be appealed, although he has said that he is "studying in detail" and has not revealed the facts.

Sangüesa City Hall "knew nothing"

The judgment of the Court of Justice of the National Court has given rise to further reactions. The City Hall of Sangüesa published a note stating that it did not know "the existence of problems that could jeopardize the granting of the donation".

He explained that the City Council "has nothing to do with" the efforts and procedures carried out so far and that it will ask to meet with the representatives of the Government of Navarra. In any case, the municipal government of Sangüesa (in the hands of UPN) has reiterated that it will try to bring forward a project that, in its opinion, is "strategic" with the government and the sponsoring company.

In Sangüesa, twelve plots of the Public Utility Mountains will be used for the construction of the mine and 20 plots or private land will be expropriated at the request of the City Hall.

A map of the land to be occupied by the Muga mine, based on the reports of the company Geoalcali. Many public lands in Sangüesa would also be required to carry out the project. Arainfo

50 kilometres of galleries buried

The Muga mine is promoted by the company Geoalcali and behind it is the multinational Highfield Resources, which is listed on the Australian Stock Exchange. About a month ago, an agreement was signed with several Chinese multinationals to finance the project.

Geoalcali estimates that the project requires an investment of over EUR 600 million. For 30 years, they want to extract a million tons of pozas a year and to do so they want to build ramps of 3 kilometers, from 350 meters depth, to open galleries of 50 kilometers in length through Sangüesa and Bald'Onsella, in Aragon.

Geoalcali wants to extract from the earth for 30 years a million tons of potash a year, for which it will build ramps of 3 kilometers, from 350 meters depth, to expand the galleries of 50 kilometers in length

Urban platforms and environmental groups have denounced that the mine would increase seismicity in the lands near the Yesa reservoir, would cause landslides and would have to endure the daily transport of 500 trucks in the villages of the area, with the consequent pollution.

In total, the mine would generate about four million tonnes of waste a year, which could be accumulated on the communal grounds of Sangüesa forming a large hill of millions of cubic metres. Massive water use is also envisaged, so the project will need annually a volume of water equivalent to that spent by 165,000 people to extract the potash.


You are interested in the channel: Ingurumena
2024-10-28 | Jakoba Errekondo
Communication to the Sagastizales
He arrived in the Basque Country in 2018. Another migrant who has become naturalized and Euskaldunized. Welcome you. A few at first, the plague by 2023.

European tortola
Protagonist of the time of pass
A Ürx’aphal is a trixte in the village that is made in Nigarrez by the alley, With his sweetheart Lagün: Kill them, hell.

November with the color of fire, the age of seeds
What is cooking for you? For me, the bonfire place, the bonfire side. It's the heart of the house, a place to cook with mime and affection. Then, a place to eat, taste, share and enjoy around the table. We entered the kitchen to eat the seasonal one.

2024-10-28 | Garazi Zabaleta
Artotxiki
Artobeltza, millet, quinoa and vegan products in Estella
As a child, Gillen and his brother Bittor Abrego Arlegi have lived in the farmhouse, in Tierra Estella, in the village of Igúzquiza. The family has been a farmer, but when the farmhouse and the plots remained in their hands, the two brothers decided to turn the project around:... [+]

Thousands of protesters in Vitoria-Gasteiz call for Álava’s macro-projects to be halted
Convened by seventeen associations, social movements and associations of Álava, thousands of people have gathered this Saturday in Vitoria-Gasteiz in the rain. The demonstration, which departed from Plaza Bilbao, has filled the Plaza de los Fueros at the end of the tour. ... [+]

2024-10-24 | Julene Flamarique
Postponed trial against Greenpeace members who denounced Caparroso's macro-finance
Greenpeace took this action in March 2021, in Navarre, against the Great Farm of the Valley of Odiet. The Macrohacienda accuses ecologists of 79 calf diseases, now the Greenpeace defense has submitted a veterinary report that denies the complaint and the trial has been postponed... [+]

Moratorium on a project in Mallorca that would be the largest macro-farm in the Spanish state
Son Vanrell, a macros farm that they built in Sineu, would have 750,000 chickens. The ecological damage would be significant: it would be the largest growth centre in the Spanish State in ammonia emissions and would absorb a third of the country’s water consumption.

2024-10-23 | ARGIA
Demonstration "Macroprojects no" on Saturday in Vitoria-Gasteiz
Over sixteen platforms have joined the initiative "Araba is not for sale" and "No to macro-projects!" with messages and organising a joint demonstration: on 26 October at 18:00 in the Plaza Bilbao of Vitoria-Gasteiz. They then sent out a message calling for participation in the... [+]

2024-10-23 | Julene Flamarique
Greenpeace submits a complaint against the Guggenheim de Urdaibai for violation of the Coast Law
The woman has filed her complaint with the National High Court and has called for "an immediate halt to the project". He warned that it would violate two laws: The National Hearing will transfer to the Ministry for the Ecological Transition and the Demographic Challenge of the... [+]

2024-10-23 | Josu Salegi
High Mill and High Mill
A dozen bertsos

The migration of birds: that beautiful but threatened enigma...
The bird migration map shows us that Euskal Herria is an interesting and rich step for migratory birds. We count around 350 species of birds for both winter and for those who come and for those who rest during the migratory journey. The longing for life and the instinct for... [+]

A sentence suspending the operation of the Muga de Sangüesa mine
The Superior Court of Justice of Navarre has annulled the authorization of the Government of Navarre to the company Geoalcali for the exploitation of the potash, following the appeal lodged by Subai Erakuntza and Ekologistak Martxan.

Eguneraketa berriak daude