"We've lost 60% of the energy in five seconds, we don't know why"

  • By the time the day dawned, electricity had returned almost everywhere. It has lagged behind the Basque Country in most parts of the Spanish State, as well as in Portugal. It seems normal today in the Basque Country, but in the early hours of the morning the suburban trains are not working in Bizkaia and Gipuzkoa, and partially in Navarre.
RTVE

29 April 2025 - 07:40
Last updated: 17:33

Twenty hours have passed since the entire Spanish electricity grid fell suddenly and completely, and neither the Spanish Government nor the supplier company Red Eléctrica have clarified what has happened. The director of Red Eléctrica Española, Eduardo Prieto, attributes the blackout to the "great oscillation" of the flow of power, rejecting the fact that it was a cybersecurity event.

At 6:00 p.m., the President of the Spanish Government, Pedro Sánchez, made his first appearance, mainly to demand "tranquility". In fact, it wasn’t until almost midnight that electricity returned to Madrid, and there were a lot of citizens away from their place of residence because they moved to go to work in the morning and couldn’t return, the streets without light, and the phones had no coincidence; people were getting nervous.

At around 11 p.m. Sánchez returned to the press to give the first explanations of what had happened. Apparently, at 12:33, the Spanish electricity grid has lost 15 gigavatio in a five-second period; about 60% of the total energy demand at the time. They do not know why, and all hypotheses and avenues of investigation remain open.

By 23:00, electricity had been recovered in 50% of the land area of the peninsula of the Spanish state, but the differences were evident. For example, in Álava, Bizkaia and Gipuzkoa it was more than 95%, in Navarre it was more than 80% and in another community it was only 15%.

By Tuesday, but by 7:00 a.m., electricity has returned to 99% of the land area of the Spanish State. It’s slower in Portugal – more than half of the residents had electricity by 5 a.m. – but they hope to “fix it in the morning.”

Back to normal?

As in the afternoon of the blackout, services have been recovered as supplies return, and will continue to do so on Tuesday. Therefore, in the Southern Basque Country, all of them will work properly, among other things, unlike some parts of Spain, the schools of the Southern Basque Country will be open.

What is not working, in the early hours of the morning, is the Cercanías de Renfe service in Bilbao and San Sebastian. Yes, but partially in Navarre.

The Bilbao metro has started operating at dawn and the Euskotren service is already operating at 100%, recovering the route between Ermua and Durango, which has cost the most to return.


You are interested in the channel: Energia krisia
Itzalaldiaren biharamunean, Espainiako Gobernuaren eta Red Eléctrica de Españaren arteko tirabirak dira nagusi

Pedro Sánchezek hornitzaile pribatuei eta Red Eléctrica de Españari egotzi die itzalaldiaren inguruko informazio gutxi eskaintzea, baina azken honek jakinarazi du "gutxi gorabehera" aurkitu dutela Iberiar penintsula osoko argindarra joatearen arrazoia... [+]


The origin of the blackout: photovoltaic installations, private companies in the area and deficiencies in the electrical infrastructure?
Red Eléctrica de España has completely rejected the possibility of cyberattack and has focused its attention on the two photovoltaic plants. “We will hold private operators accountable and activate the necessary measures to prevent this from happening again,” said Spanish... [+]

What the blackout has revealed
The social consequences of Monday’s blackout have been widely reported in the media, but has there been enough mention of what this incident reveals? These include two main issues: our dependence on energy for survival and the decline in the quality of public services that has... [+]

Electricity return works in the Basque Country
From 12:30 to 13:20, the power grid has fallen throughout the Iberian Peninsula, as well as in France, and in many parts of Western Europe. He has not yet returned to all places; it is said that it will take about six to ten hours. It has caused damage in all places, such as... [+]

Munduko energia kontsumoaren igoera eragin dute industriaren, AAren datu-zentroen eta bero boladen areagotzeek 2024an

Energiaren Nazioarteko Agentziak (IEA) astelehenean argitaratutako txostenaren arabera, %2,2 igo da energia eskaria 2024an aurreko urtearekin alderatuta, besteak beste, egiturazko arrazoi hauengatik: beroari aurre egiteko argindar gehiago erabili beharra, industriaren kontsumoa... [+]


Lurraldeko harrapariak eta energia-mendekotasuna dutenak Arabako hegoaldean jarri dira

Eusko Jaurlaritzak eta Arabako Foru Aldundiak Datu Zentroen instalazioei ateak irekitzen dizkiete horiek arautzeko legedia sortu aurretik. Bilbao-Arasur Dantu Zentroarekin, bere lehen fasea gauzatuta, eta instalatzea amesten duen Solariaren Datu Zentroarekin, 110.000 m2... [+]


2027an ixten hasi behar diren zentral nuklearrak mantentzeko eskatu diote Iberdrolak eta Endesak Espainiako Gobernuari

Espainiako Estatuko zentral nuklearrak itxi ez daitezen aktoreen presioak gora jarraitzen du. Otsailaren 12an Espainiako Kongresuak itxi beharreko zentral nuklearrak ez ixteko eskatu zion Espainiako Gobernuari, eta orain berdin egin dute Endesak eta Iberdrolak.


2025-02-13 | Gedar
Russian gas returns to Europe via TurkStream
Slovakia has announced that it will continue to receive Russian gas after the flow in Ukraine has ceased, and Transnistria has refused European "aid".

Trump announces the largest investment in history to boost Artificial Intelligence
The newly appointed President of the United States has announced an investment of $500 billion for the project called the Stargate. Companies such as OpenAI, SoftBank and Oracle will participate.

Ukraine leaves eastern Europe without Russian gas, broken with Gazprom
The Government of Volodymyr Zelensky has not renewed its contract with Gazprom and, on Wednesday morning, the Russian company has suspended the flow of gas to supply eastern Europe.

2024-12-23 | Estitxu Eizagirre
EH Bizirik has mobilized against the plan approved by the Basque Government:
"Overcoming the current capitalist model is fundamental to finding a way out to the ecological and energy emergency"
On 20 December the Basque Government approved the "provisional version" of the Sectoral Territorial Plan for Renewable Energy (PTS), following the tradition that projects that generate social conflict will be approved on the eve of the holiday. EH Activa has concentrated before... [+]

“We are not your monkeys anymore”

The Centre Tricontinental has described the historical resistance of the Congolese in the dossier The Congolese Fight for Their Own Wealth (the Congolese people struggle for their wealth) (July 2024, No. 77). During the colonialism, the panic among the peasants by the Force... [+]


Congo and cobalt
What are we willing to stay connected for?
It serves us to take this last portrait with twilight. Or the little puppet that we just asked the waiter of the pay bar in a moment. And, wow, in the back pocket of the pants that want to mimic the Levi’s come perfectly. The cell phone also serves that. So who cares that in... [+]

The UN begins the final phase of negotiations to limit plastic pollution
The summit, which runs through the city of Busan in South Korea, will last from 25 November to 1 December. The oil-producing countries and their lobbies are putting obstacles, as they do not want to limit production.

Eguneraketa berriak daude