The Vitoria Link is preferred by the Government of Navarra before Ezkio

  • The Spanish Government will announce its final decision next year, but according to the hearing of the Territorial Cohesion Advisor, Bernardo Ziriza, yesterday in the Parliament of Navarre, the Government of Navarre also seems to be in favour of the Vitoria-Gasteiz link.

19 October 2022 - 11:17
AHTren obretan, lanak geratzeko eskatuz egindako mobilizazio bat. (Argazkia: Ekin Klik)
Zarata mediatikoz beteriko garai nahasiotan, merkatu logiketatik urrun eta irakurleengandik gertu dagoen kazetaritza beharrezkoa dela uste baduzu, ARGIA bultzatzera animatu nahi zaitugu. Geroz eta gehiago gara, jarrai dezagun txikitik eragiten.

Bernardo Ciriza and Chema León, a geologist of the Government of Navarra, attended the Territorial Cohesion Committee of the Foral Parliament on Tuesday. As we know, the Government of Navarra is conducting a geotechnical and hydrological study under Aralar which would use the link of Ezkio, and therefore, in order not to delay the process any further, Ciriza announced that the project will be divided into two parts, one from Pamplona to Altsasu and the other from Altsasu/Alsasua, either from Vitoria or Ezkio. In any case, he said that the exit from the base of Aralar was very uncertain due to the need to build tunnels of 40 kilometers (two tunnels of 21 kilometers).

As explained by the geologist León, the road of Vitoria-Gasteiz is well studied geologically and is well known for having been there where many roads have already been built. It would therefore be much simpler to do the new railway out there. The Aralar sub-area would be very complicated because the Aralar sub-area is unknown and hydrological problems could occur that would affect a large part of the population. It says that “the Vitoria-Gasteiz line would be built easier and faster.”

It would be easier, it is obvious, but it has often been denounced that the new line of Vitoria-Gasteiz divided Sakana into two, so the supporters of the social train ask that it not be done out there either. The same argument is used by Geroa Bai to defend Ezkio. There is already a railway, an old road and a motorway in the ravine, and this project would add the fourth communications infrastructure.

The representatives of UPN and Geroa Bai have maintained their position, stating that the connection with the Basque Y at all costs should be made from Ezkio, otherwise Navarre will be left out of the main European routes of communication. The PSN has changed its position and supported Ciziza: the fundamental thing is that the fast train goes ahead, and that it is not so important that it goes from Vitoria or Ezkio, the important thing is that the link is done correctly and you need information to decide well. In the programme of the last foreign elections, the PSN supported Ezkio. EH Bildu, for its part, stressed that the debate is not Gasteiz or Ezkio, but TAV yes or no; that we are still on time and called for the TAV project to be rejected.

2026: An AHT island of 70 kilometres

In any case, according to Ciriza, the first high-speed trains will be in operation in Navarre by 2026. It will depart 250 km per hour and the Castejón de Pamplona 70 km will travel in 28 minutes. At present, the Alvia train is 140 kilometres per hour and takes 48 minutes.

The Navarre authorities have insisted on putting date at the end of the works, but so far it has not been complied with, and the current announcement by Ciriza is not very credible either, given that, for example, the Ta-Arrizabalaga tranche has barely begun, and it is one of the most complex subsections of this section.

But if the date was fulfilled, these 70 kilometers could remain as an TAV island, especially the 82 kilometers of Zaragoza Castejón to the south, and the 90 kilometers of Asturias-Vitoria are still in the study phase. And in the same situation is the train station of Etxabakoitz to be carried out in Pamplona. The latter, however, does not prevent a temporary station from being set up in Pamplona, as planned in the Basque capitals.


You are interested in the channel: Abiadura Handiko Trena
Polls begin in the Otsobi Council land without asking for permission
Preliminary surveys for the construction of the High-Speed Train on Otsobi Council sites have been initiated without information being provided and without request for authorisation. The Stop Surveys platform reports on the situation: "The surveys have been launched without... [+]

They call to mobilize against the TAV project running through Lapurdi
The CADE group, made up of environmental associations, has denounced that the TAV going through Lapurdi is progressing in its development. He has scheduled for 12 and 13 October in Gironde, in support of the protest organised by the Altxuak network on Earth.

Neither galgo nor hunting dog

We have been with the "summer snake" over the TAV for a few weeks and with the possibility of linking the "Basque Y" from Pamplona, from Ezkio or Vitoria.

It is disappointing to see that our People continue to depend on decisions concerned and not supported by the galgos and... [+]


The Spanish Government says that the connection of the TAV with Ezdox-Itsaso has "problems" and bets on that of Vitoria-Gasteiz
The Spanish Minister of Transport, Óscar Puente, has assured that the connection with Navarre "is the most acceptable" in Vitoria-Gasteiz, because the Eztango-Itsaso route has "technical complexity".

Works of the TAV and Renfe: cuts and headaches in the rail service of Gipuzkoa for seven years
Since the beginning of the tunnel excavation in Gaintxurizketa in 2017, the restrictions and conditions of the works of the TAV to the Renfe railway service have been constant. Now, the Spanish Ministry of Transport has announced that this service will be interrupted for several... [+]

2024-06-06 | Jule Goñi
Stop polls, key

In the spring of last year, in Sakana, in Izan and Goierri, flooding was introduced in the municipalities of these areas for the conduct of geological surveys for the works of the TAV. In the canyoning 15 surveys have been requested in the municipalities, from Erro to Olazti /... [+]


Saturday: Day against the TAV in Pamplona

Although immersed in an unprecedented eco-social crisis, the administration continues at all costs with the work of the TAV, destroying the territory and squandering the resources essential to social needs. The works of the Castejón Bridge and the Tafalla Campanas subsection,... [+]


For fair eco-social alternatives, without VAT

Next Saturday, May 11, AHT Gelditu! Navarra organizes in Pamplona the Day against the TAV. In addition, Eco-Socialist Spaces, the World March of Women and the Charter of Social Rights have called a demonstration under the motto For a Dignified Life, A Just Eco-Social... [+]


2024-04-22 | Ahotsa.info
Sakana bets on the public and social train
A massive demonstration in Alsasua calling for the cessation of TAV works and the improvement of the current rail system.

Saturday in Altsasu the demonstration "To make the train a real means of transport"
Actors against the TAV and for the railways will hold a demonstration in Altsasu on Saturday 20 April to call for the renewal of railway infrastructure and the increase in train frequency. The respondents recall the existence of an alternative and ask that this study be... [+]

They discover remains of another Basque town in Navarra and denounce that the works of the TAV can destroy them
In the village of Muru Artederreta, on the hill of Murugain, the wall of an Iron Age village has been discovered while taking samples for TAV works. The community of neighbours denounces that the construction of the mouth of a rail tunnel would destroy part of the wall.

Julio Villanueva (AHT Gelditu)
“Abiadura Handiko Trenik gabeko Nafarroa posible da”

Abiadura Handiko Trenaren inguruan mintzatu dira zenbait ekintzaile asteazkenean Iruñeko Zabaldin osatu duten hitzaldian. Italiako Val Susa bailarako adibidea bertatik bertara ezagutzeko aukera ere izan dute han sortutako mugimenduaren ordezkari bat etorri delako... [+]


Iñaki Arriola notes that to see the works of the TAV completed it will still take a few years
The Councillor for Transport of the Basque Government has acknowledged that citizenship is "tired and annoying" with the duration of the works. It is promised that the works of the concrete infrastructure of the so-called "Basque Y" will end in 2025, but the entire upper structure... [+]