The "solution" of the Basque Government after Zaldibar: incineration and fattening of cements

  • The disaster at the Zaldibar landfill and the closure of the Mutilva landfill have just forced the Basque Government to take a new order to dispose of a number of waste that has so far been destined for landfill. The solution proposed is to burn 102,500 tons of residues related to the paper industry and mix white and black slag from contaminating steel with concrete in cement plants.

26 March 2020 - 07:43
Donostiako erraustegia. Argazkia: Noaua.

Large volumes meeting in the Government: Summoned by the Department of the Environment, the owners of public and private landfills of the CWC and those responsible for the industrial sectors that deposit the most waste in landfills have come to the table: Basque Paper Cluster Association, Navarre and Basque Country Funders Association and Steel Cluster. It is 17 February, eleven days after the arrival of the Zaldibar landfill, and the Mutiloa landfill will be closed on 29 February. The meeting aims to provide a solution to the 500,000 tonnes of waste annually destined for the Zaldibar landfill of the company Verter Recycling 2002 and to the 350,000 tonnes sent to the landfill of Mutiloa de Cespa Conten, S.A. Outcome of the meeting: "There is currently no capacity to continue dumping waste in the quantity and form previously carried out," he said.

The fulfilment of the household tasks collected at this meeting would allow public and private landfill sites to inform the Basque Government of the amount of waste they have the capacity to collect, and in addition to the amount they have received so far, they could receive 440,000 tonnes of waste more per year, that is, half of the 850,000 that Zaldibar and Mutiloa landfills devoured each year.

Order 1556 of the Environment Department of the Basque Government, published in the Official Gazette of the Basque Country on 4 March, begins with all the information that has been provided so far. The Order comes when Basque society is shocked by the form of waste management that has emerged in the Zaldibar landfill and is calling for control, and appears to be putting forward drastic measures at first reading.

What to do with 2.2 million tonnes of non-hazardous waste?

Every year, 2.2 million tonnes of non-hazardous waste are deposited in CAPV landfills. The Basque Government gives this information in Order 1556. In 2018, 2.5 million tonnes of waste came to landfill (if the law was complied with, landfills had to make the last effort to recycle all these tons of waste). In fact, ARGIA has obtained official data on the waste that was deposited in all CAPV landfills in 2018, data from the Basque Government: this list details the types of waste collected in each landfill and the specific kilograms thereof. To define the type of residue, the European RSI code is used, which assigns a specific number to each type of residue as standard cataloging.

The Government Order 1556 lays down the following rules for non-hazardous waste producers and landfills authorised for receipt. The order is valid for at least 12 months and aims to reduce the amount of waste that is deposited in the landfill. The measures it has taken are as follows:

– Reception of indigenous waste in CAPV landfill sites. The disposal of waste generated outside the CAPV to CAPV landfills will require special authorisation from the Environment Department.

The Order forces the paper industry to burn sludge. In 2018, there were 102,500 tonnes for incinerators each year. The types of waste involved in the burning in particular are destined sludge for paper production (RSI 030305), effluent sludge (RSI 030311) and waste paper rejection (RSI: 030307). Impure papers have a high concentration of chlorine and when incinerated they produce dioxins that are totally harmful to health.

– Another waste stream related to the paper sector is sludge from the production of Kraft pasta (LER 030309), which can be physically valued at the cement factory, but which is currently not possible to manage all that is generated, and which will require special authorisation from the Basque Government for landfill. In 2018, 109,000 tonnes were reached.

Black and white steel slag (LER 100201 and 100202). Landfill sites may not accept it for construction sites. The Order obliges the black and white slags of the steel industry to be "valued" and enables waste found after recovery to be dumped. In practice, what the order says "to value" is to confuse with concrete in cements. Cement mixed with slag is used in road construction to level the ground. According to data on waste dumped in landfills in 2018, the implementation of this measure would result in a reduction of almost 140,000 tonnes of white and black scum per year in landfills. On the other hand, these residues are contaminated and along with the cement the contamination will spread on the grounds here and there.

– Construction and demolition waste may be recovered in mobile installations, but the rejection or “rejection” that remains unvalued must be commuted to the approved fixed installations for further recovery at fixed installations. Almost 130,000 tonnes of this type of waste were dumped in landfills in 2018 (LER codes 170101, 170102, 170103, 170107, 170904). Gypsum is the toxic material that prevents the reuse of construction and demolition residues, and both gypsum and non-gypsum achieve a very high or almost zero recovery of these residues.

– Sludges from the urban sewage treatment plant should be recovered and landfill will require special authorisation from the Government. In 2018, 7.8 tonnes were recorded.

Sands and portions of iron castings (green moulding) (LER 100906, 100908, 100910). Its valorization in cements for clinker production is also proposed. However, the Order indicates that the three CAPV cement plants cannot respond to most of this type of waste. In 2018, 1111111,000 tonnes were registered. These wastes also need special authorisation from the Basque Government for landfill.

Detailed vehicles. Once the cars are moved to the graveyard of the cars, the parts that can be reused are removed and, after passing through a kind of press, they are moved to the landfill in a compact way. The order states that "only the removal fractions of this waste from the authorised secondary demetalisation facilities shall be allowed into landfill." But it also says that it cannot be rigorous in that standard, because in the CAPV there is not enough capacity to value this type of waste. Special authorisation from the Basque Government will be needed to bring this type of waste to landfill. In 2018, 109 thousand tonnes were reached.

 


You are interested in the channel: Zaldibarko zabortegiaren krisia
Remember the disaster of the Zaldibar landfill on its fourth anniversary
Zaldibar Argitu has held an event on Sunday. There is no news in the “Basque oasis”, they say, “the Basque Government repeated that everything did well.”

Two companies in Lapurdi are penalising for unauthorized dumping into the Zaldibar landfill
The Baiona Hearing states that the company Etcheverry Mindurri, located in Basusarri, must pay a fine of 150,000 euros and the CBA Artola of San Juan de Luz, of 100,000 euros.

2023-10-03 | ARGIA
The provisional sealing of the Zaldibar landfill will also be carried out by the Government
The department of Arantxa Tapia has asked the company to do this work, but Verter has not answered. The works will ensure the stability of the landfill for a period of “five or six” with a budget of 750,000 euros.

Annulment of statements by three Government technicians by judicial review
On Thursday the three technicians from the Basque Government's Environmental Department were to be declared, but the courts of justice have not been able to do so. They must explain the granting of the Integrated Environmental Authorisation to Verter Recycling.

Three Basque Government technicians declare Thursday, three years after the accident
Three technicians from the Department of the Environment of the Government are going to testify in a case investigating crimes against the environment at the Zaldibar dump. The Zaldibar Argitu platform and the Charter of Social Rights of Euskal Herria have called a concentration... [+]

2023-02-14 | Ula Iruretagoiena
Sewers

Visiting urban waste collection and reduction sites should be a compulsory school tour. Open a cookie pack to swallow two inner cookies and mentally construct the package surface path. The shame of human activity lies in destiny. Ultimate desolate landscape of the sins of... [+]


Zaldibar landfill will not be sealed yet
After three years of the disaster, Councilor Tapia told the press that "technical inspections" are being carried out, that the landfill is "stable and secure", but that it is not yet sealed even if authorised. Verter Recycling seems to have no will.

2023-02-06 | ARGIA
They call for political responsibility in the case of Zaldibar, on the third anniversary of the collapse
The workers Alberto Sololuze and Joaquín Beltran, called by the Zaldibar Argitu platform, have been honoured in the Eitzaga district three years after being caught in the landfill. They reaffirm the need to clarify the matter and call for political responsibilities.

Waste management in Bizkaia
The environmental organisation has highlighted in a report the deficiencies in waste management in Bizkaia since the disaster in the Zaldibar landfill. He explains that the draft of the new waste management plan has not yet been approved and is in force in 2016. It attributes to... [+]

Zaldibar Argitu platform will remind Sololuze and Beltrán three years after the end of the landfill
Next Sunday at noon, 5 February, the Zaldibar Argitu platform will remind the workers Joaquín Beltran and Alberto Sololuze and will require clarifications and responsibilities.

The mountain has deteriorated, our lives have fallen
Death, drama, work, mourning, pain, anguish. Limits, measures, passions, love and family. Carnival. Zaldibar and pandemic; landfill life. The latest joint work of the theatrical companies Axut and Artedrama is about to be released: Catastrophe. The first action will take place... [+]

2022-10-05 | ARGIA
Zaldibar Argitu: “Lakua ez da neutrala izan, auziaren parte izan da”

Europako Batzordeak beste behin adierazi du Eusko Jaurlaritzak legedia bete zuela Zaldibarko zabortegiaren kasuan. Zaldibar Argitu plataformak nabarmendu du Lakuak bidalitako informazioa soilik izan duela kontuan Bruselak.


Two

In February, two years have passed since the Zaldibar landfill fell. In March comes the second anniversary of the pandemic, when we stay home for two months. Two disasters. The second covered the first, but the management of the Eitzaga disaster taught us how the pest was to be... [+]


Eguneraketa berriak daude