The Basque Government will pass an invoice of EUR 3.5 million to the company Verter Recycling

  • The Department of the Environment of the Basque Government has reported that it will send the company that owns the landfill of Zaldibar, Verter Recycling 2000, S.L., the first invoices of the work being carried out in the landfill. The first block is provided with EUR 3,420,988.71.

08 June 2020 - 10:22
Elkarretaratzea Zaldibarren bi langileak desagertu zirela lau hilabete igaro direnean. Argazkia: ESK.

The Basque Government took the lead in all the stabilisation and control work on the landfill since the landfill waste fell on 6 February, due to the company’s lack of capacity to do so.

The invoice for the first block to be paid by the company includes the stabilization of the sliding and the generation of safe slopes that allow the search for the two missing workers, the opening of access to urgent work points, the control of the environmental and health impact of the population, the control and extinction of the fire by heavy machines and the cooperation of air resources, the creation of safety deposits for the waste or the design of the groundwater control network.

To date, the Environment Department has carried out landfill sites worth EUR 9 million.

The Ertzaintza has found traces of crime

The news was published in the journal “El Correo” and subsequently received by the news agency Efe. According to the report presented by the Ertzaintza in the court, the newspaper has found evidence of criminality in the management of the company Verter Recycling in the landfill, which has been closed down. Ertzaintza has on several occasions identified irregularities in the management of waste collected in an unauthorised manner. The report estimates that there are indications of two offences. On the one hand, he is convicted of a crime against the environment by putting the natural environment and people’s health at serious risk. On the other hand, it says that action has been taken against workers' rights.

4 months after the disappearance of Beltrán and Sololuze

On 6 June, four months have passed since the workers disappeared from the landfill Joaquín Beltrán and Alberto Sololuze. On that day, mobilizations were carried out, inter alia, to demand the discovery of the bodies of the two workers.


You are interested in the channel: Zaldibarko zabortegiaren krisia
Remember the disaster of the Zaldibar landfill on its fourth anniversary
Zaldibar Argitu has held an event on Sunday. There is no news in the “Basque oasis”, they say, “the Basque Government repeated that everything did well.”

Two companies in Lapurdi are penalising for unauthorized dumping into the Zaldibar landfill
The Baiona Hearing states that the company Etcheverry Mindurri, located in Basusarri, must pay a fine of 150,000 euros and the CBA Artola of San Juan de Luz, of 100,000 euros.

2023-10-03 | ARGIA
The provisional sealing of the Zaldibar landfill will also be carried out by the Government
The department of Arantxa Tapia has asked the company to do this work, but Verter has not answered. The works will ensure the stability of the landfill for a period of “five or six” with a budget of 750,000 euros.

Annulment of statements by three Government technicians by judicial review
On Thursday the three technicians from the Basque Government's Environmental Department were to be declared, but the courts of justice have not been able to do so. They must explain the granting of the Integrated Environmental Authorisation to Verter Recycling.

Three Basque Government technicians declare Thursday, three years after the accident
Three technicians from the Department of the Environment of the Government are going to testify in a case investigating crimes against the environment at the Zaldibar dump. The Zaldibar Argitu platform and the Charter of Social Rights of Euskal Herria have called a concentration... [+]

2023-02-14 | Ula Iruretagoiena
Sewers

Visiting urban waste collection and reduction sites should be a compulsory school tour. Open a cookie pack to swallow two inner cookies and mentally construct the package surface path. The shame of human activity lies in destiny. Ultimate desolate landscape of the sins of... [+]


Zaldibar landfill will not be sealed yet
After three years of the disaster, Councilor Tapia told the press that "technical inspections" are being carried out, that the landfill is "stable and secure", but that it is not yet sealed even if authorised. Verter Recycling seems to have no will.

2023-02-06 | ARGIA
They call for political responsibility in the case of Zaldibar, on the third anniversary of the collapse
The workers Alberto Sololuze and Joaquín Beltran, called by the Zaldibar Argitu platform, have been honoured in the Eitzaga district three years after being caught in the landfill. They reaffirm the need to clarify the matter and call for political responsibilities.

Waste management in Bizkaia
The environmental organisation has highlighted in a report the deficiencies in waste management in Bizkaia since the disaster in the Zaldibar landfill. He explains that the draft of the new waste management plan has not yet been approved and is in force in 2016. It attributes to... [+]

Zaldibar Argitu platform will remind Sololuze and Beltrán three years after the end of the landfill
Next Sunday at noon, 5 February, the Zaldibar Argitu platform will remind the workers Joaquín Beltran and Alberto Sololuze and will require clarifications and responsibilities.

The mountain has deteriorated, our lives have fallen
Death, drama, work, mourning, pain, anguish. Limits, measures, passions, love and family. Carnival. Zaldibar and pandemic; landfill life. The latest joint work of the theatrical companies Axut and Artedrama is about to be released: Catastrophe. The first action will take place... [+]

2022-10-05 | ARGIA
Zaldibar Argitu: “Lakua ez da neutrala izan, auziaren parte izan da”

Europako Batzordeak beste behin adierazi du Eusko Jaurlaritzak legedia bete zuela Zaldibarko zabortegiaren kasuan. Zaldibar Argitu plataformak nabarmendu du Lakuak bidalitako informazioa soilik izan duela kontuan Bruselak.


Two

In February, two years have passed since the Zaldibar landfill fell. In March comes the second anniversary of the pandemic, when we stay home for two months. Two disasters. The second covered the first, but the management of the Eitzaga disaster taught us how the pest was to be... [+]


Eguneraketa berriak daude