And when they showed the contract of the Gloucester incinerator ... 100 million pounds more expensive

  • In June of last year, a young man went on a 15-day hunger strike in Gloucester, United Kingdom, to require the authorities to show the total contract of the incinerator Javelin Park they are building there. When it was published at Christmas, it came as a surprise: it is going to cost the citizens 30% more than what has been said so far. Protests have multiplied and some politicians have begun to demand the implementation of an independent audit.

08 January 2019 - 10:50
Urbaser hilabeteotan ari da bukatzen Javelin Park erraustegiaren eraikuntza, Gloucesterren. (Argazkia: Mark Watkins, Gloucestershire Live)n
Zarata mediatikoz beteriko garai nahasiotan, merkatu logiketatik urrun eta irakurleengandik gertu dagoen kazetaritza beharrezkoa dela uste baduzu, ARGIA bultzatzera animatu nahi zaitugu. Geroz eta gehiago gara, jarrai dezagun txikitik eragiten.

Sid Saunders had reason to keep the hunger strike for fifteen days before the Gloucester City Hall, insisting that the authorities display the contract: after a long month of shooting, they have finally shown the papers and among them it has appeared that the contract to which they have so far referred – signed in 2015 and hitherto kept secret – is much more expensive than has been said: Costs of £500 million (EUR 557.5 million) have risen from EUR 600 million (EUR 669 million) to the highest. The paper had been done by Ernst & Young's office. The contract of the incinerator Javelin Park is owned by Urbaserri, the company that has the incinerator of Gipuzkoa

As the scandal continues to spread, several ediles in Gloucester have begun to complain that they had voted for misinformation, that they have also deceived as all citizens and that they have asked for an independent audit of what is going on. The owner of the chronicle offered by the media Gloucestershire Live says: "Javelin Park incinerator: Opposition councillors have called for an independent investigation into the cost increase." Gazette continued to say: "Politicians want answers on the scandalous £600 million cost of the Zubieta incinerator."

Demonstration on Gloucester Street to request the suspension of the incinerator's contract. (Photo: Gazette)

As you can read in the chronicles, you also begin to talk about the famous Javelin Park incinerator in Britain, with problems similar to those of other incinerators. Firstly, the municipalities of Gloucester and its district will be taxed for years. Then, because the actual costs are higher than those mentioned and, consequently, for other public administration programmes – schools, social policies… – this waste management service leaves less money than the declared, as the tonnage sent to burn will cost a lot more expensive: £189 per tonne. It is also untrue that smoking was cheaper than alternative waste treatment. And finally, Gloucester forces us to undo the policies organized to make better use of the waste generated, as it cannot allow less waste to be burned to balance the incinerator’s accounts.

The association against the incinerator NoMoInGlo (No Monster Incinerator in Gloucester) has called for today, Tuesday, 8 January, a protest rally at the door of the Javelin Park building.

In the call, under the motto "Money to Roast," from Charles Dickens' famous tale, Scrooge says: "The environment? Huh... nonsense! Services for children? Huh... nonsense! Finally give me the project of a nice and fat business...

2019-01-10, updatedn.La association NoMoInGlo (No Monster Incinerator in Gloucester) has in video summarized in his Facebook account the protest of January 8.

Punchline TV has offered the following pictures of the protest:

 

 


You are interested in the channel: Errausketa
2023-09-08 | ARGIA
They organize the human chain against incineration on the day of the Concha races
The Anti-Incineration Movement denounces that waste management in Gipuzkoa continues to worsen. It is explained that the San Sebastian incinerator has increased pollution and reduced selective collection, and that the new projects planned in the country will go further in this... [+]

2023-08-04 | Ilargi Manzanares
GHK recognises 42 days of untreated waste incineration
They indicate that they have done so “provisionally” for “maintenance”. It is also said that all “environmental demands” have been met and that no rules have been broken.

2023-05-28 | Zero Zabor
Dear Iñaki Usabiaga
Many of those involved in the mobilizations against the Zubieta incinerator in Gipuzkoa met Iñaki, the oldest activist with 80 years of history. In the photo you can see the work done in the mountains to the incinerator in 2018 with a young militant.

2023-04-24 | Zero Zabor
Authorities recommend not to eat eggs from chickens in the Parisian capital because they are contaminated with dioxins, furans and PCBs
The Health Authority of the region of Pil-de-France, the capital of Paris and the entire metropolis of the area, has recommended that citizens not consume eggs from small hens of their houses: a study commissioned by the public authorities confirms what the ToxiWatch foundation... [+]

2023-02-27 | Zero Zabor
Faced with the uncontrolled expansion of toxic PFAS, the European Commission is initiating its regulation
A study promoted by major European media reveals that PFAS is distributed in thousands of black spots across the continent. PFAS (per- and polyfluorinated compounds, ‘Per- and polyfluoroalkyl substances’), which you have not heard of, are particularly polluting and have... [+]

2022-09-08 | Zero Zabor
On Sunday they will protest at the beach of La Concha against the incinerators of Zubieta and Bergara
The Anti-Incineration Movement has called on Gipuzkoan citizens to mobilise against the incineration of waste on 11 September in Donostia at the same time as the regattas are held. The EAM militants have been demonstrating for years their protest against the incinerator built in... [+]

2022-06-20 | ARGIA
Mass mobilisation against the Larramendi incinerator in Bergara
The Larramendiko Arnasa group has called for a demonstration against the incinerator that the company Valogreen wants to build in Bergara on Sunday noon. They denounce the Government ' s attitude.

2022-04-26 | Zero Zabor
The incinerator Zabalgarbi earns 17 million in subsidies, despite not really valuing the waste
The Ekopol Association, which investigates the characteristics of ecological sustainability, social and environmental crises and climate change in the Basque Country, has analysed the result of the activity carried out by the Zabalgarbi incinerator in Bizkaia in 2020. The most... [+]

2022-04-20 | Zero Zabor
The Prosecutor's Office denounces the incinerator of Barcelona for infringing environmental regulations
In 2018, the citizens of the Airenet platform complained to the courts that the incinerator of Sant Adriá de Besòs, which burns the metropolitan waste of Barcelona and its metropolitan area, repeatedly violates the law. In the framework of its investigation, the public... [+]

2022-01-31 | Zero Zabor
Kutsadura toxiko handia detektatu du ikerketa batek Espainia, Txekia eta Lituaniako hiru erraustegiren inguruan

Zero Waste Europe-k (ZWE) Espainia, Txekia eta Lituaniako hiru erraustegiri buruz argitaratu duen ikerketa berri batek egiaztatu du instalazio horien inguruetan kutsadura maila handia dagoela, eta hori arriskutsua litzateke ingurumenerako eta gertu bizi diren pertsonen... [+]


2021-12-23 | ARGIA
Jaurlaritzak Zumarragan erraustegi bat eraiki nahi duela salatu du ELAk

Zumarragan 2023 amaierarako eraiki nahi duten plastikoak tratatzeko plantan pirolisia erabiliko da olioa lortzeko (takoil), eta olio hori plastiko berria eta erregaiak egiteko erabiliko da. "Hondakin solidoak errez erregaia sortzen du, eta Europar Batasunaren beraren... [+]


Bergarako erraustegi proiektuaren erruz, 200 langileko kooperatiba bat herritik joan dela salatu du Udalak

Bergarako Udalaren webgunean irakur daiteke albistea izenburu honekin: 200 langileko kooperatiba batek Bergaratik joatea erabaki du Valogreene-k bertan ezarri nahi duelako hondakinen planta. "Paper-industriaren hondakinen tratamendurako planta Bergaran ezarri aurretik,... [+]


2021-11-24 | Leire Artola Arin
The Bergara Incinerator Project Round Table Raises Public Concern
The representative of Ecologists in Action accused Greene of “lying” and “hiding data” from the public, and warned of the harm of dealing with waste with pyrolysis. The project managers, however, have explained the "benefits" of the plant and have ensured that pyrolysis is... [+]

2021-11-04 | Zero Zabor
Concentration in Bergara against the incinerator
The Ekologistak Martxan movement called for a concentration in Bergara on 4 November, in protest at the construction of a plant to gasify waste from paper mills. This environmental group has been the first to denounce the true nature of the waste plant they want to build in the... [+]

New Bergara plant
You say pyrolysis, I say incinerator
The Alicantina company Greene Waste to Energy S.L., promoted by the Euskadi Paper Cluster, has announced the construction of a waste treatment plant for paper plants in Bergara.

Eguneraketa berriak daude