Automatically translated from Basque, translation may contain errors. More information here. Elhuyarren itzultzaile automatikoaren logoa

They want to end the expansion of the Esa reservoir by 2027

  • The works began 22 years ago, but the construction of the reservoir has had many problems, and the works are still going on. In response to the request of Río Aragón, the Confederación Hidrográfica del Ebro, CHE, replies that the work is scheduled for completion in 2027.
Argazkia: CHE

29 September 2023 - 11:35
Last updated: 2023-09-30 22:03

The construction of this infrastructure consists of eleven chapters, one of the most significant being the one that took place in 2013: On the right side of the Yesa reservoir there was a landslide that forced the demolition of 103 houses built in the area.

Since then, eleven other studies have been carried out on the hillside and, although with significant nuances, in all of them the topic of mobility of these soils has been explained, with the risk that this may entail. As a result of all this, the project is now in its fourth adaptation, and asked about the Rio Aragón association fighting the dam, CHE replies: “The current implementation plan expires on 30 November 2027.” In that reply he said that work was currently under way on the fourth adaptation of the project and that, until its completion, it could not provide further information.

As explained in Arainfo, the Rio Aragón association has denounced that six years ago the fourth adaptation began and that CHE has not yet given significant reasons to explain the delay that is taking place. In any case, it specifies that these adaptations will be very complicated because “they will have to respond to problems that occur at a depth of 100 meters”.

For example, due to the torrential rains, the water entering through the soil cracks increases the instability of the slopes and Río Aragón says that they will have to rebuild some built reliefs to channel the waters that have undergone movements.

Libyan Marsh Disaster

Work began in 2001 and was due to end in 2005, but at the moment it is completed in 2027. They started with a budget of EUR 113 million, but it is already EUR 500 million. Now, moreover, the disaster caused by the floods and the fall of two dams in Libya has shaken the fear of the Yesa dam. According to Nadhir Al-Ansari, an engineer and expert in water resources, the breakdown of the dams in Libya should not only be sought in the floods, but in their management. In addition, disasters in reservoirs are sometimes also affected by construction errors.

Construction works have slowed down considerably in two decades, but they continue to move forward because the political leaders of the construction, the Government of Spain, consider that the movements taking place on the slopes are very small or reach a certain balance. In any case, according to another news report known in September, it has also been noted by satellite that the Yesa reservoir is unstable.

 

 


You are interested in the channel: Esa urtegia
Enlargement of the Esa reservoir
The ghost of the breakup always there
After the cold drop in Valencia, the shadow of the disaster has spread to other places: what would happen if a giant storm like this hit the swollen reservoir of Esa? Would the dam hold up? Would the water overflow? The questions are there and so are the fears, because it would... [+]

2024-11-20 | ARGIA
They warn that the expansion of the Yesa dam is "a time bomb" if cold water drops are placed in it
The Aragonesist Chunta has asked the Government of Spain to review the project to expand the Yesa dam, following the recent cold drop disaster. In case of suffering this kind of rainfall, That would not have enough capacity to release all that water, so it would be "a serious... [+]

A sentence suspending the operation of the Muga de Sangüesa mine
The Superior Court of Justice of Navarre has annulled the authorization of the Government of Navarre to the company Geoalcali for the exploitation of the potash, following the appeal lodged by Subai Erakuntza and Ekologistak Martxan.

Closure of the extension of the Esa reservoir
According to the Rio Aragon Association, the expansion of the Esa reservoir is paralyzed by "insecurity". This group requests the suspension of the contract and the revision of the project. They call on the Ebro Hydrographic Confederation to accept "unfeasibility".

Satellite warn of the instability of the Yesa reservoir
Geological studies have warned on more than one occasion and now the warning comes from satellite surveillance: The Yesa reservoir is not stable. Copernicus, the European Union’s Earth observation programme, has detected a ‘movement’ on the slopes of the reservoir.

D. Alfredo Ollero Ojeda
“Rivers are sinking deeper and deeper into their channels”
The Ebro is the largest river in the Basque Country. We have spoken on its shore, at the entrance to Zaragoza, where Ollero lives, accompanied by the slow lertxuna, the crazy song of birds and the gentle flow of the river, the afternoon that has erupted spring at 33 degrees,... [+]

Ingeotyc geology recommends not to extend the Yesa reservoir
It concludes that the right side of the reservoir remains unstable and therefore there is a level of risk. The report was prepared by geologists Valentín Ibarra and Tomás Morales of the company Ingeotyc on behalf of the City Council of Sangüesa.

Remírez states that the Government of Spain acts rigorously in the Yesa dam, 22 years after the beginning of the works
The Vice-President of the Government of Navarre, Javier Remirez, explained in the Parliament of Navarre a study on the safety of urgency which was completed fifteen months ago and which has not been published so far. The investigation was carried out on behalf of the Government... [+]

Extension of the Esa reservoir is welcomed by the report of the Ministry of Transition
Finally, the report of the Government of Spain on the safety of the Yesa reservoir has appeared, which has been “lost”, and allows the work of the reservoir to continue.

They denounce the loss of the report commissioned by the Government of Spain on the Yesa dam
The Spanish Government's Ministry of Transition commissioned the Spanish College of Road and Port Engineers to see what the organization said about the reservoir's viability.

Suspension of the water project from Salazar to Yesa
The Ebro Hydrographic Confederation has withdrawn from its hydrological plan the project of building a dam in the village of Aizpurgi, in the Navarre Pyrenees, and its drive to the Yesa reservoir through an underground canal.

Analysis
Navarre reservoirs below the minimum: What has evidenced the drought?
The dry summer we have had in many places in Euskal Herria is already noticeable. According to data collected by the Ebro Hydrographic Confederation (CHE), the water stored in Navarre is well below the average of the last decade and in the case of the Yesa reservoir is 29% of... [+]

Korrontearen atzetik
Piszinan aurrera eta atzera aspertu egiten dira nonbait, eta 1989ko abenduaz geroztik ibaietan, urtegietan, lakuetan eta itsasoan egin dute igeri. Miño, Ebro, Sil, Bosnia-Herzegovinako Neretva ibaia gerra garaian... Nafarroako Esa urtegia, Eskoziako Ness laku famatua,... [+]

What are the risks of the large Yesa potash mine?
The Muga project, approved by the Government of Spain, provides for a mine of 1,700 hectares between the Navarros municipalities of Xabier and Undués de Lerda, very close to the Yesa reservoir. Experts say it would contaminate the rivers and aquifers in the area, sink the soil... [+]

2020-10-23 | ARGIA
"Vicelehendakari Remirez puts at risk the safety of ships"
The vice-president of the Government of Navarra and responsible for civil protection, Javier Remírez, has criticized the attitude of Subai Erakuntza to the seismic movements that are taking place in Navarre around the Yesa dam and in recent weeks. In the following lines one can... [+]

Eguneraketa berriak daude