The expansion of the Esa reservoir is paralysed. This has been reported by the Rio Aragon Association. For 22 years, attempts have been made to expand this reservoir and since then there have been only "problems". "There is no security and viability cannot be guaranteed," the Association stressed. "The Yesa reservoir has two operators in recent weeks, one in administrative tasks and the other in safety. In this way, it is being achieved not to interrupt the contract that is underway with the company UTE Yesa," said Rio Aragón. In fact, two employees cannot be accused of "abandonment" and of suspending the employment contract. Belen Ausejo Urbizi says that in addition to moving the right slope other problems are emerging to the Ebro Hydrographic Confederation and the Spanish Ministry: "The one on the left also has problems. Some of them are poorly built and some should move 40 meters," they say. The defence wall of the Sigues people is also poorly built with a fourth published modification. "The Ministry has not acted clearly in expanding this reservoir and it is not now easy to have information," he said.
Faced with this situation, the platform Sin más Esa and the Rio Aragon Association request the "non-feasibility" and the paralysis of Esa's expansion works and the suspension of the contract. "The project should be reviewed from the top down and the current press set. In this way, the security level should be lowered to 460 and the mistakes made so far should be corrected," they say.
The expansion of the Esa reservoir began in 2001 and the budget planned at that time has quadrupled. They have spent a total of EUR 400 million. Insecurity has called into question the extension of the reservoir, particularly because of the movements taking place on the right side.
Nafarroako Pirinioetako Aizpurgi herrian presa bat eraiki eta lur azpiko kanal baten bidez ura Esa urtegira eramateko proiektua kendu egin du Ebroko Konfederazio Hidrografikoak bere plan hidrologikotik.
Euskal Herriko hainbat tokitan izan dugun uda idorra ari da nabaritzen jadanik. Ebroko Konfederazio Hidrografikoak (CHE) jasotako datuen arabera, Nafarroan biltegiratutako ura azken hamarkadako batez bestekoaren oso azpitik dago, eta Esako urtegiaren kasuan gehienezko mailaren... [+]
Espainiako Gobernuak onartu duen Muga proiektuak 1.700 hektareako meatzea aurreikusten du Nafarroako Xabier eta Zaragozako Undués de Lerda udalerrien artean, Esako urtegitik oso gertu. Adituen ustez, besteak beste, inguruko erreka eta akuiferoak kutsatuko lituzke, lurra... [+]
Esako urtegiaren inguruan eta azken asteetan Nafarroan izaten ari diren mugimendu sismikoez erakutsitako jarrera dela eta, Sustrai Erakuntzak gogor kritikatu du Javier Remirez Nafarroako Gobernuko presidenteordea eta Babes Zibileko arduraduna. Ondorengo lerroetan irakur daiteke... [+]
Azken bi egunetan nahasmen handia egon da Esako urtegia handitzeko lanen inguruan. Asteartean Teresa Ribera Espainiako Gobernuko Trantsizio Ekologikorako ministroak esan zuen ez zela urrats bat gehiago aurrera egingo segurtasuna erabat ziurtatu arte. Aturando Esa (Esa Gelditzen)... [+]
Uraren Kultura Berria Fundazioak (FNCA gaztelaniazko sigletan) Esako urtegiari buruzko azken txosten ofizialak aztertu ditu eta ondorioztatu du urtegiaren eskuineko hegalak "ezegonkorra" izaten jarraitzen duela eta, beraz, "segurtasuna ez dagoela bermatuta".
"Esan eta manipulazio informatiboa" izeneko idatzia zabaldu dute Esa Ez-Lanak Gelditu eta Río Aragón elkarteek hainbat hedabidetan. Agintari politikoek, azpiegitura horrek dakarren arriskua ezkutatzeko darabilten hizkera salatu dute.