The City Hall of Amurrio and the Administrative Boards jointly submit allegations to Solaria’s energy generation project

  • Local authorities have questioned the environmental impact study and have warned that it will have a severe environmental impact and that a joint study will have to be carried out for future projects.
Artikulu hau CC BY-SA 3.0 lizentziari esker ekarri dugu.

10 July 2024 - 07:16

The City Hall of Amurrio, in collaboration with the Lezama Administrative Board, the Barambio Administrative Board and the Larrinbe Administrative Board, in that the layout of the evacuation infrastructures directly affects them, has presented in the Territorial Delegation of Industrial Administration of Álava, allegations of the Solaria energy generation project. These claims concern the municipality affected by the evacuation infrastructure of the PV solar plant (2-3-4) to the point foreseen in substation 400 of Zierbena.

The allegations presented question various aspects of the environmental impact study presented by Solaria. According to local authorities, this study fails to comply with the recently approved General Urban Management Plan (PGOU) and, in some cases, seriously affects the local environment.

In addition, it is considered that the evacuation infrastructure can be used for other photovoltaic and/or wind projects whose location is not yet known. In this case, and given that it has access and connection permits in the same node of the transport network, a joint environmental study should be carried out to evaluate the interactions in the territory.

Finally, the signatory administrations agree that once the submitted claims have been resolved, the City Council, together with the Administrative Boards concerned, will re-examine the adoption of new initiatives in this regard.


You are interested in the channel: Energia berriztagarriak
2025-02-19 | Estitxu Eizagirre
by Francisco Vaquero
“The Basque Country is the region that is fighting the most against renewable macroprojects”
Vidas irrenovables (Non-renewable lives) has filmed the consequences of "renewable" macroprojects. The Basque and French subtitles are being prepared) by this independent director, raised in the rural area of Extremadura (Cabeza del buey, Spain, 1985) in the documentary. The film... [+]

In defense of Labraza
"(The purpose of the Oion Plenary) is clear, to legitimize by law the energy megaprojects with significant irregularities in the processing"

Last Wednesday we had a hard and unpleasant day, not only for Labraza, but also for all the towns where we are threatened by a wind,... [+]


The government changes its renewable land plan to make more space for large-scale wind turbines
On December 20, the Basque Government approved the provisional version of the plan and a large number of “low and medium” capacity areas are now listed as “medium and high” capacity.

2025-02-04 | Mikel Aramendi
THE ANALYSIS
Will the world’s largest dam that China wants to build burn down?
The announcement by the Chinese government in the last breath of last year that it will launch a large hydroelectric project in the lower basin of the Yarlung Zangbo River, which has not flooded the waters, seems to have set them on fire among us. We can say that the comments... [+]

2025-02-04 | Estitxu Eizagirre
"The energy transition in debate"
Round table between Mikel Otero and Aitziber Sarobe on Wednesday in San Sebastian
On 5 February, Mikel Otero, head of ecological transition at EH Bila, and Aitziber Sarobe, natural conservationist, will take part in a panel discussion in San Sebastian entitled "Energy transition in debate: opportunities and risks". This event is organized jointly by four... [+]

2025-02-03 | Estitxu Eizagirre
The company informs the City Council of Zizurkil that they will not install wind turbines in Ezkeltzu
Green Capital has notified Zizurkil City Council verbally of its decision to "definitively cancel" the Ezkeltzu project. The City Council welcomed the cancellation of the project, which "raised serious doubts about the damage it could cause to the environment, landscape and... [+]

2025-01-27 | Julene Flamarique
Renewable energy beats fossils in EU electricity generation in 2024
Electricity production from gas has declined for the fifth year, and overall fossil electricity generation is at an all-time low, according to Ember’s European Electricity Review.

2024-12-23 | Estitxu Eizagirre
EH Bizirik has mobilized against the plan approved by the Basque Government:
"Overcoming the current capitalist model is fundamental to finding a way out to the ecological and energy emergency"
On 20 December the Basque Government approved the "provisional version" of the Sectoral Territorial Plan for Renewable Energy (PTS), following the tradition that projects that generate social conflict will be approved on the eve of the holiday. EH Activa has concentrated before... [+]

2024-12-17 | Usurbilgo Noaua
There is no wind farm at the moment, on Mt. Ezkeltzu between Usurbil and Zizurkil
The wind farm project, which was planned to be built in Ezkeltzu, will not be implemented for the time being. In February 2022, the intention to build a wind farm in Ezkeltzu was known. From that point on, the subject has taken a journey, but at the moment it seems that the... [+]

2024-12-10 | Leire Ibar
Construction of a new 74,000 panel photovoltaic power plant in Navarra begins
GES-Global Energy Services has launched the solar power generation project in Olite, one of the largest in the Basque Country. It will have a power of 50 MWp and will have a total of 74,000 solar panels, so the facilities are expected to be launched before the end of the... [+]

2024-12-05 | Estitxu Eizagirre
Nine other wind turbines are planned, this time in Beizama and Bidania-Goiatz, in Gipuzkoa
Finerge intends to install nine macro-wind turbines in Beizama and Bidania-Goiatz, of 229.5 meters each, with a combined power of between 45 and 50 MW. Among the windmills, six roads would be built, which would also be taken to the land of Errezil. The company has presented to... [+]

The year of the popular platform Meaka-Irimo
Sometimes we need a threat to know the importance of what is at risk. And the magnitude of that threat depends on the strength that we feel within us to respond to a possible aggression. As soon as you realize, you see yourself working hard to protect those who are at risk of... [+]

2024-11-08 | Egurra Ta Kandela
Strategic lines of the Basque Government
If the reading of the Renewable Energy Sector Territorial Plan (PTS EBB) for farmers and livestock farmers was disappointing – and it was – it was not that it was much happier to read the report of responses to 4,217 allegants in this regard in July 2023. It was published on... [+]

Eguneraketa berriak daude