AAV in the Southern Basque Country: An investment of 15 billion euros to reach Irun at high speed?

  • A demonstration against the high-speed train will take place in Pamplona this Saturday, called by the platform AHT Pause, at 12:00 hours from the Provincial Council. The construction of the railway line between Castejón and Pamplona continues and the Spanish Ministry of Transport considers that this part could be operational by 2027.

14 February 2025 - 11:50
Last updated: 13:37
Agintariak Hiriberri eta Tafalla arteko Monte Planoko tunelean. Nafarroako Gobernua.

At the end of January, the association AHT Pause denounced that the workers working in the AVE of Navarre are in a situation of slavery, given the testimonies of some of the workers who had worked there for this purpose. The Adif, in charge of the construction of the railways in Spain, refutes the allegations. Saturday’s demonstration will denounce these working conditions and the fact that this project “enslaves society as a whole” with the following heading: “AAV enslaves us. Let’s break the k-aht of progress.”

The works of the Navarre Fast Train began in 2009 and in January the General Director of Transport of the Spanish Government, Berta Miranda, said that the Castejon-Pamplona section could be operational by 2027. Now they are doing the part between Tafalla and Campanas and, according to him, it will be finished by 2026 at the latest. The Pamplona Station will arrive in the neighborhood of Etxabakoitz, but since the construction of this will be delayed a lot, the government says that the train will leave without the Pamplona station and that 20 minutes will advance in this part.

The Knot of Thyme

The fast train will go from Pamplona to Sakana, but there is still a big knot to untie, as the Spanish government has not decided whether it will go from Ezkio or Vitoria. Government officials, both with the PP and the PSOE, have repeatedly expressed their support for the Vitoria-Gasteiz link, but no final decision has yet been taken. However, in Sakana, surveys are being carried out to better analyze –not without problems– the Ezkio project. It is expected that the Ezkio project –55 kilometres and 21 of them the tunnel under Aralar– would cost 2 billion euros and the Vitoria-Gasteiz project would cost around 700 million euros.

The Basque Government, the PNV, Geroa Bai and the UPN are pushing hard for the link to be made from Ezkio, but not without a slot, since the Provincial Council of Álava, which commands the PNV, for example, supports the link in Vitoria-Gasteiz. The ecological deterioration in both options is considerable, especially in Aralar, although supporters of Ezkioko say that the Vitoria-Gasteiz option would also severely damage the Barranco, the old road and the motorway that it now has, because it would add the AVE railway and thus saturate the valley.

The high speed... Up to Irun

One of the main arguments of the supporters of the Basque projects of the AVE has always been to have a good and modern connection with Europe. However, the French government has informed the Spanish government that the fast train will not arrive in Hendaye until at least 2042.

A $15 billion investment?

It is always wrong to get involved in the issue of the cost of AAV. The construction of the Basque Y began in 2006, but it still does not have an end date, mainly because the stations of the capitals are not yet built. The Minister of Transport and Sustainable Mobility of the Spanish Government, Oscar Puente, recently visited San Sebastian this week and said that already 5 billion euros have been spent in the Basque Y and almost 4 billion euros are still to be invested. The investments to be made in the Navarrese part are still unclear, but they can amount to at least 3,000-4 billion euros; the amount can vary considerably if it goes from Ezkio or Vitoria-Gasteiz. In any case, high-speed investment with both projects could approach €15 billion.


You are interested in the channel: Abiadura Handiko Trena
Adif says that the situations of labor slavery denounced in the works of the AHT are "false"
After receiving the scandalous testimony that AHT Geldi denounces the existence of situations of labor slavery in the works of the High-Speed Train of Navarre, the company Adif that promotes these works has had to respond publicly: "They're a lie."

AHT Pause denounces the existence of situations of slavery in the works of the AVE of Navarre
The workers of the fast train that is being built in Navarre denounce that they are in a state of slavery during the press conference of the association AHT Pause in Pamplona.

They denounce that the AVE will lead to a large expropriation of agricultural lands in Álava
Representatives of the Añana and Trebiñu gangs, as well as farmers and ranchers in Álava, have denounced that they suffer "enormous institutional contempt" for the work of the AVE. More than two million square meters of “fertile land” will be expropriated in these places... [+]

For a quality public rail service for the Ribera

In recent weeks we have been reading "proposals" for the recovery of the railway line Castec-Soria and the maintenance of the Tudela train station in its current location, or for the construction of a new high-speed station outside the urban area with the excuse of the supposed... [+]


2024-12-18 | ARGIA
The Basque Y will not connect with Ipar Euskal Herria until at least 2042
The French Government has confirmed to the Spanish Government that the High-Speed Train will not reach Hego Euskal Herria (Irun link) until at least 2042 years later. It is not among the priorities of Paris.

TAV: The Spanish Government is considering a "third" alternative for connecting the Basque 'Y'
The Secretary of State for Sustainable Transport in Spain, José Antonio SANTANO, has stated that the Basque Government has admitted a resource on the connection of Ezpied-Itsaso, which would not "harm" Aralar.

2024-11-27 | Julene Flamarique
TAV works in the CAV are delayed until at least 2027
The Basque Government expected the High-Speed Train to be ready by 2027 when the Astigarraga-Hernani stretch ends in February 2024. The Basque Government has now launched a tender for the works of the Arkaute link, which has made available to the company Euskal Trenbide Sarea,... [+]

Polls begin in the Otsobi Council land without asking for permission
Preliminary surveys for the construction of the High-Speed Train on Otsobi Council sites have been initiated without information being provided and without request for authorisation. The Stop Surveys platform reports on the situation: "The surveys have been launched without... [+]

They call to mobilize against the TAV project running through Lapurdi
The CADE group, made up of environmental associations, has denounced that the TAV going through Lapurdi is progressing in its development. He has scheduled for 12 and 13 October in Gironde, in support of the protest organised by the Altxuak network on Earth.

Neither galgo nor hunting dog

We have been with the "summer snake" over the TAV for a few weeks and with the possibility of linking the "Basque Y" from Pamplona, from Ezkio or Vitoria.

It is disappointing to see that our People continue to depend on decisions concerned and not supported by the galgos and... [+]


The Spanish Government says that the connection of the TAV with Ezdox-Itsaso has "problems" and bets on that of Vitoria-Gasteiz
The Spanish Minister of Transport, Óscar Puente, has assured that the connection with Navarre "is the most acceptable" in Vitoria-Gasteiz, because the Eztango-Itsaso route has "technical complexity".

Works of the TAV and Renfe: cuts and headaches in the rail service of Gipuzkoa for seven years
Since the beginning of the tunnel excavation in Gaintxurizketa in 2017, the restrictions and conditions of the works of the TAV to the Renfe railway service have been constant. Now, the Spanish Ministry of Transport has announced that this service will be interrupted for several... [+]

2024-06-06 | Jule Goñi
Stop polls, key

In the spring of last year, in Sakana, in Izan and Goierri, flooding was introduced in the municipalities of these areas for the conduct of geological surveys for the works of the TAV. In the canyoning 15 surveys have been requested in the municipalities, from Erro to Olazti /... [+]